Understanding the project organization.
On the image below, the structure example has several items structured hierarchically. Each level of the structure shows a responsible manager that can be edited according to project changes.
This structure has a direct relationship with the OBS defined for the company:
For each EPS, Project or WBS level there is a Responsible Manager allocated.
When a user is registered, it will become available to him the elements of the project according his allocation on the OBS and the access to information defined for that OBS level. For example: A user is registered with the role of Scheduler on the “Information Technology” division on the “Line of Business 1”. For that to happen, the user must have editing and creating permission on projects of OBS element “IT Projects for Line of Business 1”.